    Home » First GE HA turbines to be installed at UAE Power Plant
    Business

    First GE HA turbines to be installed at UAE Power Plant

    March 17, 2021
    Facebook WhatsApp Twitter Pinterest LinkedIn Telegram Tumblr Email Reddit VKontakte
    The UAE’s first two GE HA gas turbines have been delivered, and are currently undergoing installation and commissioning works at the 1.8 gigawatts (GW) Hamriyah Independent Power Plant. The project is expected to be the most efficient power plant in the Middle East’s utilities sector, contributing towards UAE Energy Strategy’s goal of reducing the carbon footprint of power generation. GE is supplying a total of three 9HA.01 units and other power generation technologies for the facility. It will also provide parts, repairs and maintenance services for power generation assets at the site for a period of approximately 25 years.

    First GE HA turbines to be installed at UAE Power Plant

    Co-developers GE Energy Financial Services (“GE EFS”) and Japan’s Sumitomo Corporation (“Sumitomo”) signed an approximately 25-year Power Purchase Agreement (PPA) with Sharjah Electricity, Water and Gas Authority (SEWA) in 2018 to develop, build and operate the plant. Following financial close in 2019, co-developers along with Shikoku Electric Power Company and Sharjah Asset Management (“SAM”), the investment arm of the Government of Sharjah, formed a joint venture company – Sharjah Hamriyah Independent Power Company (SHIPCO) – to build, own and operate the project, which is the first independent combined cycle power plant in Sharjah.

    GE’s HA technology is the fastest growing fleet of heavy-duty gas turbines globally and has already set two world records for efficiency, one each in the 60 hertz and 50 hertz segments of the power market. Higher efficiency levels mean that less fuel needs to be consumed and that there are fewer emissions per megawatt of electricity generated. In fact, using three GE 9HA.01 units in combined cycle operations can help SEWA reduce carbon dioxide emissions by up to 4 million tons per year, compared to current levels. This is the equivalent of taking 1 million cars off the UAE’s roads.

    A team of over 1,300 people has been mobilized for the project. In addition to the two HA units, GE Gas Power has also already delivered several other pieces of key equipment at the site, including two steam turbines, two gas turbine generators, two steam turbine generators, two Heat Recovery Steam Generators (HRSG), two condensers, power island e-rooms and step-up transformers. Almost all the civil works, up to 85 percent of the procurement, and up to 60 percent of construction and commissioning works at the Hamriyah project, are now complete.

    Related Posts

    Brent crude steadies after 2% drop amid Iran sanctions

    August 25, 2026

    South Korea starts first Arctic container ship trial

    August 24, 2026

    Alibaba raises HK$80 billion for AI and cloud growth

    August 24, 2026

    Japan trade reaches records with imports leading exports

    August 21, 2026

    Wall Street rebounds on lower yields and healthcare surge

    August 20, 2026

    South Korea car exports set July high at $6.24 billion

    August 14, 2026
    Latest News

    Kisangani hub active as DR Congo launches Ebola vaccination

    August 29, 2026

    Algeria wildfires leave 12 dead and 54 injured in north

    August 27, 2026

    South Korea inbound tourism rises 20.8% in July

    August 26, 2026

    Air Arabia sets five weekly Sharjah Gdansk flights

    August 26, 2026

    EU expands Ebola response with €2.1 million PCR tests

    August 25, 2026

    Brent crude steadies after 2% drop amid Iran sanctions

    August 25, 2026

    South Korea starts first Arctic container ship trial

    August 24, 2026

    Alibaba raises HK$80 billion for AI and cloud growth

    August 24, 2026
    © 2026 News of Maldives | All Rights Reserved
    • Home
    • Contact Us

    Type above and press Enter to search. Press Esc to cancel.